5333 Connecticut Ave. Building Blog

Site crane complete.

21 Mar 2014

Final length of crane arm.

21 Mar 2014

Crane counterweight.

21 Mar 2014

Crane hook in place.

21 Mar 2014

Crane hook.

21 Mar 2014

Second part of crane arm.

21 Mar 2014

First part of crane arm.

21 Mar 2014

Crane height complete.

21 Mar 2014

Top of crane in goes into place.

21 Mar 2014

Crane cab.

21 Mar 2014

Fourth piece of crane.

21 Mar 2014

Third piece of crane.

(Click for full photo.)

21 Mar 2014

Work outside site, north.

21 Mar 2014

Manhole vault and cover, transferred.

21 Mar 2014

Work outside site, south.

21 Mar 2014

Second part of crane in place.

21 Mar 2014

Second part of crave going up.

21 Mar 2014

First crane part  put in place.

21 Mar 2014

Site crane parts delivered.

21 Mar 2014

Maxim Crane, twenty stories tall.

(Click for full photo.)

20 Mar 2014

Maxim Crane.

20 Mar 2014

Working on Military outside the fence.

20 Mar 2014

Pumping truck and cement trucks in concert.

18 Mar 2014

Visit from cement pumping truck.

18 Mar 2014

Putting out the welcome mat.

18 Mar 2014

Backhoe digging down.

18 Mar 2014

Baby dozer starts the day.

18 Mar 2014

Site after early finish.

17 Mar 2014

Moving plastic cover from pit.

17 Mar 2014

Work on the snowy secreted pit.

17 Mar 2014

Ice covered webcam window.

17 Mar 2014

29. Week of Monday, 17 March, 2014

        Welcome Live Stream Building Blog Slideshows Q&A Misc

Previous / Next

Monday, 17 March, 2014 to

Saturday, 22 March, 2014

Blog, Photos and Videos in reverse chronology.

Select thumbnail at the left for larger photo.

• Saturday, 22 March, 2014

There was just a bit of work this morning. The

Hertz backhoe dug around the bottom of the

onsite crane, while the crane hook rose and

lowered a half dozen times, without any apparent

load. The Maxim Mobile Crane gyrated for an hour

then left the site just before 9A. At 9:30A

supplies were delivered; the backhoe unloaded and

the site crane moved the load to the upper, north

side of the site. At 10A the onsite crane operator

climbed down and by 10:30A, the site was closed

for the day.

• Friday, 21 March, 2014

- Video - A BIG Day

Today was a BIG day that made previous days

look dull and previous machines look small. Turns

out the secreted pit was for the foundation of the

permanent construction crane, PCC. The Maxim

Mobile Crane that arrived yesterday hoisted the

parts of the site PCC into place and the crew

bolted the pieces together. The Maxim Mobile

Crane and the new PCC were so tall they reached

off the top of the webcam screen, so still photos

were used to document the work in the clouds. As

a side show almost totally eclipsed by the cranes,

a the backhoe/dozer worked outside the site on

Military Road, digging and filling dump trucks in

preparation for a new manhole vault with manhole

covers, which was delivered webcam front and

center at 10:30A. Work at both places continued

until dusk at 7P. (5:59 min )

•  Thursday, 20 March, 2014

- Video

- The two backhoes worked behind the fog until it

cleared at 9A, when the Hertz backhoe moved

the large box “generator” from the entrance way

to the street-level strip of site along Military.

There was just superficial scurrying until a

backhoe/dozer and dump truck started work just

off site (far left screen). At 1P a very large Maxim

mobile crane stole attention, even though a

backhoe was dashing back and forth with buckets

of cement for the pit. Work went on around the

crane until it stood up just before 3P; it reached

over twenty stories tall -- far beyond the upper

limit of the webcam. The crane exercised for

about an hour and then folded as the site closed

at 4P. (2:37 min)

• Wednesday, 19 March, 2014

- Video

- Today was a full-site, three-ring circus with all

machines and all crew performing on all four

retaining walls, on pit work, and on earth moving.

At 9:30A dump trucks started backing into the

small upper workspace as the backhoe moved

away the dirt that shrunk the upper workspace

even further. And around noon it was all done in

the rain. Earth moving stopped within an hour of

the rain, but pit work continued, 2:30P a cement

truck unloaded, and just before 3P a large square

yellow machine was delivered. (1:23 min)

• Tuesday, 18 March, 2014

- Video

- One of two baby bull dozers started the day by

cleaning the snow off the upper portion of the

site. At 8A the crew prepared a white parking mat

for the 9:30A arrival of a new machine that

pumped cement through hoses into the pit. And

to supplement the new machine were a stream of

twenty one cement trucks. The resident backhoe

-- usually the “star of the site” but today a

second look --  dug down further at the north wall.

(Fast forward with the browser controls. 4:56

min)

• Monday, 17 March, 2014

Winter’s last hurrah covered the webcam window

with ice and the construction site with six and a

half inches of snow. And surprisingly, there was

work on the site. At 6:45A the crew was working

on the secreted project; the hertz backhoe lifted

off large plastic sheets used yesterday to cover

secreted drainage pit. The additional work on the

secreted pit was over by 10A.

[end page]