5333 Connecticut Ave. Building Blog

Off-site drainage work.

15 Mar 2014

Secreted project is drainage pit?

15 Mar 2014

Secreted work.

13 Mar 2014

Working outside the fence.

13 Mar 2014

Top floor parking lot.

13 Mar 2014

Perfect personification pose.

12 Mar 2014

Metal box disappears into northwest corner.

12 Mar 2014

Metal box drug into northwest corner.

12 Mar 2014

Work deep at the southern retaining wall.

12 Mar 2014

End of the day deep.

11 Mar 2014

Crew down south.

11 Mar 2014

Even the baby dozer.

11 Mar 2014

Full dance floor.

11 Mar 2014

Yellow Hertz backhoe.

10 Mar 2014

Load of wood on Military.

10 Mar 2014

Backing in for a load.

10 Mar 2014

28. Week of Monday, 10 March, 2014

        Welcome Live Stream Building Blog Slideshows Q&A Misc

Previous / Next

Monday, 10 March, 2014 to

Saturday, 15 March, 2014

Blog, Photos and Videos in reverse chronology.

Select thumbnail at the left for larger photo.

☆ Video

• Saturday, 15 March, 2014

- Video

- A field trip revealed the secreted Connecticut

Ave project to be a deep hole about 25 yards by

20 yards covered with a rebar grid, resembling a

drainage pit. The drainage hypothesis was

supported by site crew working outside the site

on the curb gutter drain on the south east corner

of Kanawha St and Connecticut Ave. Today was a

earth moving only; there was no work on the

drainage pit. The resident backhoe and dozer dug

down two thirds of the site and loaded backed-up,

dump trucks on the higher, north east third of the

site.  (1:29 min}

• Friday, 14 March, 2014

- Video

• Pre-dawn work started promptly with the Hertz

backhoe and crew working on an unseen project

below the Connecticut wall. Occasionally, the

Hertz backhoe could be seen as it lifted high it’s

shovel. After 1:30P the forklift stretched up from

the secreted project to retrieve several buckets

of cement from a cement truck. The resident

backhoe and dozer dug down two thirds of the

site and loaded dump trucks -- that had to back

on the site --  on the higher, north east third of

the site. (The time-lapsed video was slowed; fast

forward with the browser controls. 4:56 min)

• Thursday, 13 March, 2014

Another day of un-inspired construction. Work

started late and slowly. The highest level of the

site, the north east third, looked like a parking lot,

with the work done down another fifteen feet in

the other two thirds of the site. The resident

backhoe worked, too deep to see, on the south

west corner. The Hertz backhoe worked on the

Connecticut Ave side, delivering the first cement

on site to some secreted project.

• Wednesday, 12 March, 2014

Work was very eclectic today, or maybe it was

just scattered. The backhoe started the day

digging further down the Kanawha side retaining

wall, assisting the crew. At 9:30A there was a

small rush of dump trucks. At 10:45 a story-tall

metal container was delivered on site, and the

Hertz backhoe drug it into the northwest corner,

so deep it was out of the view of the webcam.

There was work on the site entrance and a few

more dump trucks.

• Tuesday, 11 March, 2014

☆  Video - Full Dance Floor

Everybody danced today. Work started with a pre-

dawn light dance. All four earth moving machines

were active most of the day -- the little dozer

even grabbed several shovels full of dirt to fix the

entrance ramp. The resident backhoe and

bulldozer were joined by the Hertz backhoe in

digging deeper down the site, from the edges

inward. Any machine digging at the west

Connecticut side (bottom screen) was too low to

be seen from the webcam. The dump trucks

slowed the Military traffic and their own progress

by the need to back onto the site. The crew was

also back at work very deep on the south

retaining wall (screen right), putting in retaining

boards and tie backs (We slowed the time-lapsed

video to enhance the dance; fast forward with the

browser controls. 4:39 min)

•  Monday, 10 March, 2014

- Video

- A new, yellow Hertz backhoe started work on

the site, but it’s job was not to assist the resident

backhoe and bull dozer in earth moving but to

asset the forklift in accepting and placing a

flatbed load of wood and another flatbed load of

steel beams. The first modest wave of dump

trucks arrived at 10:30A, then at 12:30P and at

3P for a moderate amount of earth moving today.

(1:14 min)

[end page]