5333 Connecticut Ave. Building Blog
Select thumbnail for larger photo of
comparison of Monday, 09 June, 2014 to Saturday, 14 June, 2014
Panorama looking north.
14 June 2014
Cement delivered at gate.
14 June 2014
Mini dozer at gate.
14 June 2014
East side looking north.
14 June 2014
Storing supplies on a small site.
14 June 2014
Site Closeup.
14 June 2014
Excavator still at gate.
13 June 2014
Multi-levels on third deck.
13 June 2014
Rebar and piping on third deck.
13 June 2014
Site Closeup.
13 June 2014
AM meeting and multi-level third deck.
12 June 2014
Site Closeup, with excavator on far left center.
12 June 2014
Working on Conn Ave wall.
11 June 2014
First patch if cement on third deck.
11 June 2014
AM gathering, looking north.
11 June 2014
Site Closeup.
11 June 2014
Panorama, Kanawha looking north.
10 June 2014
Looking from SE corner downhill to NW corner.
10 June 2014
Third deck grows north during today.
10 June 2014
Work continues on south side third deck.
10 June 2014
Site Closeup.
10 June 2014
Third deck from south.
09 June 2014
Third deck from north.
09 June 2014
Third deck, first floor.
09 June 2014
Three mature trees on Military.
09 June 2014
Small work space on Connecticut Ave side.
09 June 2014
Site Closeup, three levels.
09 June 2014
41. Week of Monday, 09 June, 2014
Welcome
Live Stream
Building Blog
Slideshows
Q&A
Misc
Monday, 09 June, 2014 to
Saturday, 14 June, 2014
Blog, Photos and Videos in reverse chronology.
Select thumbnail at the left for larger photo.
Saturday, 14 June, 2014
As the rest of the week, most of the work was on
the south side of the third deck -- hidden from the
webcam behind the trees. This third deck, which
is the ground floor, covers the entire site and is
being built in different levels and with more
complicated accouterments than the two below-
ground parking floors.
Thursday, 12 June, 2014
The small backhoe excavator started the day on
the ground floor of the north side, but since the
site was officially “out of the dirt,” the backhoe
was moved by crane up to the gate level. The
different levels of the third deck were more visible
as it grew from south to north.
Tuesday, 10 June, 2014
The third deck was extended further north but in
multi levels. The small excavator worked in the
last square of basement dirt.
Monday, 09 June, 2014
Rebar on the second deck and work on the third
desk south side. According to a cement
supervisor, they are waiting for DC inspectors to
inspect drainage plumbing to finish cement on
ground floor north side and be “out of the dirt.”
[end page]