5333 Connecticut Ave. Building Blog

Select thumbnail for larger photo of

comparison of Monday, 16 June, 2014 to Saturday, 21 June, 2014

Panorama

21 June 2014

New level at gate NE corner.

21 June 2014

Texture and level patchwork SW corner.

21 June 2014

Cement pillars for second floor.

21 June 2014

New cement floor NW corner.

21 June 2014

Site Closeup.

21 June 2014

New cement NW corner.

20 June 2014

Another level for the north east corner.

20 June 2014

Pillars for fourth deck aka second floor.

20 June 2014

Site Closeup.

20 June 2014

Different level center site.

19 June 2014

Work on ground floor aka third deck.

19 June 2014

Rebar web on second deck.

19 June 2014

Site Closeup.

19 June 2014

Different level center site.

18 June 2014

Ground level grows northward.

18 June 2014

Ground level meets street level.

18 June 2014

Finishing the north side of the second floor (garage).

18 June 2014

Site Closeup.

18 June 2014

Work center site.

17 June 2014

Clutter on third deck.

17 June 2014

Cement on third deck.

17 June 2014

Rebar work in small workspace on Connecticut Ave.

16 June 2014

Site Closeup.

16 June 2014

42. Week of Monday, 16 June, 2014

        Welcome Live Stream Building Blog Slideshows Q&A Misc

Previous / Next

Monday, 16 June, 2014 to

Saturday, 21 June, 2014

Blog, Photos and Videos in reverse chronology.

Select thumbnail at the left for larger photo.

• Saturday, 21 June, 2014

The week ended as it started, working on the

ground floor aka third deck, first floor. The site

supervisor answered several questions precipitated

by this week’s activity; for example, why are

there so many levels to the ground floor and why

is it taking so much longer to complete the

ground floor. And while comparing Monday

morning photos with Saturday evening photos

clearly shows progress, the activity of each hour

appeared small and tedious.

• Friday, 20 June, 2014

Another level has been added to the north east

corner. According to the site supervisor in the

Q&A, this ground level is the most difficult and

time consuming because of the different levels

that accommodate the interior and exterior

features.

• Thursday, 19 June, 2014

- Video

- The Site Supervisor answered four new

questions. Several additional levels were added to

ground floor (first floor, third deck) as it grows

northward. In addition, the pillars for the second

floor are being prepared on the south side. (1:19

min)

• Wednesday, 18 June, 2014

Ground level grows northward, while finishing

second level (garage.)

• Tuesday, 17 June, 2014

- Video

Between 9A and 12N, the crew laid the tile that

extended the ground floor; the activity was center

screen, however, like much of the construction,

the movements appeared to the webcam small

and tedious. What was noticeable was the crew

working, not down in a site pit but at almost

street level. (2:24 min)

- Spoke with a Penn State architecture student

who was working for Baker Cement for summer

job experience. He indicated the first floor, on

which they were working now, was the ground

floor under the building AND the surrounding

landscape. That is why the multi-levels for

gardens and ponds, etc and that is why it is

taking longer. This level will take another month

or so. The next level will have the outline of the

building. Subsequent levels will go up faster.

• Monday, 16 June, 2014

The surveyors were on site more often recently,

suggesting the work needed to more precise; it

certainly was more tedious.

[end page]