Previous / Next
Monday, 18 August, 2014 to
Saturday, 23 August, 2014
Blog, Photos and Videos in reverse chronology.
Select thumbnail at the left for larger photo.
Saturday, 23 August, 2014
The North of the sixth level was prepared for
cement.
Friday, 22 August, 2014
Columns for the seventh level arose in the
Northwest side.
Thursday, 21 August, 2014
Work prepared level six for cement. There was a
late morning guided tour of the site.
Wednesday, 20 August, 2014
The main work was on level six level as the floor
gang forms were completed.
Tuesday, 19 August, 2014
Work started as weaving rebar and wire for the
sixth level. Crew was walking freely, at eye level
to the third-floor Building Blog cameras. Although
we could not see the details, the noises of
construction continued well past 7P.
Monday, 18 August, 2014
The sixth floor gang forms were pronounced safe
and secure when the ports-pots were moved up
today. The rest of the day was floor gang forms
for the sixth level, stretching almost all across the
building, and new cement maintenance for the
fifth level.