5333 Connecticut Ave. Building Blog

Gate from the South.

16 Aug 2014

Column forms on the North.

16 Aug 2014

Sixth level from the North.

16 Aug 2014

Compare: Big Picture from SE Corner.

16 Aug 2014

5333 crane over 5323 building.

15 Aug 2014

View from Northwest corner.

15 Aug 2014

Laying the sixth level.

15 Aug 2014

Underside of floor gang form.

15 Aug 2014

Kyle putting up legs of floor gang form.

15 Aug 2014

15Aug14Startof6thLevel

Compare: Big Picture from SE Corner.

15 Aug 2014

Storage on the new cement.

14 Aug 2014

Compare: Big Picture from SE Corner.

14 Aug 2014

Delivering new legs for the floor gang form.

13 Aug 2014

Pillars for the sixth level.

13 Aug 2014

Compare: Big Picture from SE Corner.

13 Aug 2014

New pillars for sixth level.

12 Aug 2014

Compare: Big Picture from SE Corner.

12 Aug 2014

Morning exercise.

11 Aug 2014

Northwest corner.

11 Aug 2014

Compare: Big Picture from SE Corner.

11 Aug 2014

Compare: Big Picture, across Connecticut Ave.

11 Aug 2014

50. Week of Monday, 11 August, 2014

        Welcome Live Stream Building Blog Slideshows Q&A Misc

Previous / Next

Monday, 11 August, 2014 to

Saturday, 16 August, 2014

Blog, Photos and Videos in reverse chronology.

Select thumbnail at the left for larger photo.

• Saturday, 16 August, 2014

Cement continued on the fifth level and the gang

form continued to grow for the sixth level.

•  Friday, 15 August, 2014

The floor gang form for the sixth level was

extended from the South side, and across the

middle of the site. This new level offers a good

study of the legs and underside of the floor gang

forms. Column forms were erected on the North

side. The Blog also realized that the 5333 crane

swings into the air space above the Chevy Chase

Towers apartment building at 5323 Connecticut

Ave.

• Thursday, 14 August, 2014

The floor gang form for the sixth level was started

on the South side, while the North side was being

prepare for cement.

• Wednesday, 13 August, 2014

A busy day of preparing the fifth level for cement

and completing more pillars for the sixth level.

• Tuesday, 12 August, 2014

Heavy rain from 9A to 3P curtailed major activity

but not all. A few crew in long, yellow slickers

worked through a steady rain and several deluges

to provide drainage, and a few more crew

attended to duties in the covered levels

• Monday, 11 August, 2014

Today was weaving wire and rebar and preparing

the fifth level for cement. And the sixth level was

started with new cement pillars on the Southwest

side of the fifth level.