Saturday, 16 August, 2014
Cement continued on the fifth level and the gang
form continued to grow for the sixth level.
Friday, 15 August, 2014
The floor gang form for the sixth level was
extended from the South side, and across the
middle of the site. This new level offers a good
study of the legs and underside of the floor gang
forms. Column forms were erected on the North
side. The Blog also realized that the 5333 crane
swings into the air space above the Chevy Chase
Towers apartment building at 5323 Connecticut
Ave.
Thursday, 14 August, 2014
The floor gang form for the sixth level was started
on the South side, while the North side was being
prepare for cement.
Wednesday, 13 August, 2014
A busy day of preparing the fifth level for cement
and completing more pillars for the sixth level.
Tuesday, 12 August, 2014
Heavy rain from 9A to 3P curtailed major activity
but not all. A few crew in long, yellow slickers
worked through a steady rain and several deluges
to provide drainage, and a few more crew
attended to duties in the covered levels
Monday, 11 August, 2014
Today was weaving wire and rebar and preparing
the fifth level for cement. And the sixth level was
started with new cement pillars on the Southwest
side of the fifth level.