35. Week of Monday, 28 April, 2014

        Welcome Live Stream Building Blog Slideshows Q&A Misc

Previous / Next

Monday, 28 April, 2014 to

Saturday, 03 May, 2014

Blog, Photos and Videos in reverse chronology.

Select thumbnail at the left for larger photo.

• Saturday, 03 May, 2014

From 7A to Noon, the crew filled the foundation

with the loads of a stream of cement trucks.

• Friday, 02 May, 2014

- Work began today at 6:30A, again. However,

this time there was work in earnest all the sunny

day. The crew erected gang forms and filled each

with cement via the crane. The Deere excavator

played on his gravel pile. The ant colony analogy

is impossible to avoid; the large movements of

the first six months of excavation make the

construction activity look slow and tedious. In

addition, the morning glare and the strobe effect

of fast moving clouds made the time-lapse video

not worth watching.

• Thursday, 01 May, 2014

- Making up for the rain day, the crane operator

climbed into place at 6:30A but abandoned his

post by noon. Threatening skies and an ominous

weather report kept activity to a minimum. The

Deere excavator received and spread several loads

of gravel.

• Wednesday, 30 April, 2014

- A half day of work in a full day of rain. Most of

the crew moved slowly in their big yellow slickers

and succumbed to the rain -- heavy at times --

and by 11A only the smaller, yellow, Deere

excavator on the new eastern hill remained to

received several truck loads of gravel. The site

was abandoned to the storm by noon.

• Tuesday, 29 April, 2014

- Video

- Work now stretches from just before 7A to

often after 5P. And today most of the long day

was in the drizzle and rain and viewed through

1:42 min of raindrops. Before 7A three

“managers” surveyed the site progress. During

the gray day, the excavators and a skidsteer

spread a truck load of gravel to make a new

extended mountain of far-east, drive way. The

crane and soggy crew continued to transfer

cement from a queue of trucks to foundation and

walls forms.(1:42 min)

• Monday, 28 April, 2014

- Video

- Work resumed today as it ended Friday, a three

ring circus. The backhoe filled dump trucks at the

gate. Queued cement trucks unloaded from

Military Road to the crane bucket and then to the

foundation footings and walls in the northwest

corner. And in ring three, the crew continued work

on the retaining south and west walls. (1:38 min)