5333 Connecticut Ave. Building Blog

Select thumbnail for larger photo of

comparison of Monday, 22 September 2014 to Saturday, 27 September, 2014

Southeast corner behind the building.

27 Sep 2014

Start of Level 10 aka Floor 7.

27 Sep 2014

Compare: Big Picture from SE Corner.

27 Sep 2014

Removing gang form from cement column.

26 Sep 2014

Compare: Big Picture from SE Corner.

26 Sep 2014

Working Level 9 SW in the rain_2.

25 Sep 2014

Working Level 9 SW in the rain_1.

25 Sep 2014

Compare: Big Picture from SE Corner.

23 Sep 2014

Supplies to Level 9.

19 Sep 2014

Level 9 continues North.

19 Sep 2014

Compare: Big Picture from SE Corner.

22 Sep 2014

56. Week of Monday, 22 September, 2014

        Welcome Live Stream Building Blog Slideshows Q&A Misc

Previous / Next

Monday, 22 September, 2014 to

Saturday, 27 September, 2014

Blog, Photos and Videos in reverse chronology.

Select thumbnail at the left for larger photo.

Worked on Level 9 aka Floor 6 and started Level

10 on Friday.