Saturday, 16 November, 2013
- VIDEO YouTube - Saturday Started with a Bang
-- Literally
The site manager arrived early at 6:37A, and by
7:03A -- on a Saturday morning -- the big
backhoe was revved up and in action. At 7:25A
the first of a caravan of dump trucks arrived.
(Minutes before, you can see them on
Connecticut Ave. at the bottom of the frame.) By
7:54A the first of a dozen cement trucks arrived
to work on the Kanawha St. side (screen right and
the camera box at the top left corner), and by 9A
there were five cement trucks on site. The small
bulldozer and the construction forklift took over
the activity from the large backhoe. Finally, by
12:33P the major construction activity was
finished, and only the welder and forklift continued
the rest of the day.
Friday, 15 November, 2013
- VIDEO YouTube
Same multi-activity as yesterday, but added
construction trailer to south east corner at
10:10A.
Thursday, 14 November, 2013
☆ VIDEO YouTube
Busy day on the construction site. Welding
continued on the Military St. side (screen left
behind the trees); the Jurassic Giraffe and cement
trucks continued building a metal structure on the
south east corner, and included Jurassic Park
sound effects (off screen right and in the left
corner camera box); and the large backhoe and a
string of dump trucks continued removing the
mount of dirt along Connecticut Ave (center
screen front).
Monday, 11 November, 2013 -
Wednesday, 13 November, 2013
- Continued welding on the Military St. side, and
started hole digging with Jurassic Giraffe on the
Kanawha St. side,