New cement on SE Corner.

09 Aug 2014

Compare: Big Picture from SE Corner.

09 Aug 2014

Compare: Big Picture, across Connecticut Ave.

09 Aug 2014

Fifth level arrives at the gate.

08 Aug 2014

New delivery, Grunley or not?

08 Aug 2014

Southeast corner wired for cement.

08 Aug 2014

Compare: Big Picture from SE Corner.

08 Aug 2014

Compare: Big Picture, across Connecticut Ave.

08 Aug 2014

Southeast corner catching up.

07 Aug 2014

Kanawha eye level.

07 Aug 2014

South side.

07 Aug 2014

Northwest corner.

07 Aug 2014

Compare: Big Picture from SE Corner.

07 Aug 2014

Compare: Big Picture, across Connecticut Ave.

07 Aug 2014

Kanawha eye level of the fourth level, aka first floor.

06 Aug 2014

From the SE corner. 

06 Aug 2014

Relocating supplies to West side across multi-level site.

05 Aug 2014

Relocating supplies, view from SE corner, 2.

05 Aug 2014

Relocating supplies, view from SE corner.

05 Aug 2014

Northwest corner.

05 Aug 2014

I know I'n not supposed to have favorites, but...

05 Aug 2014

Big Picture.

05 Aug 2014

Site Closeup.

05 Aug 2014

Site from Southeast corner.

04 Aug 2014

SE corner catching up.

04 Aug 2014

Kanawha street level, SW corner.

04 Aug 2014

Southwest corner, fifth level.

04 Aug 2014

Morning meeting on Northwest fourth level.

04 Aug 2014

Big Picture.

04 Aug 2014

Site Closeup.

04 Aug 2014

49. Week of Monday, 04 August, 2014

        Welcome Live Stream Building Blog Slideshows Q&A Misc

Previous / Next

Monday, 04 August, 2014 to

Saturday, 09 August, 2014

Blog, Photos and Videos in reverse chronology.

Select thumbnail at the left for larger photo.

The building is quickly advancing upward, so this

week we have moved the progress comparison

focal point from the NW corner of the site to the

following two points;

• directly across Connecticut Ave

• the Southeast corner on Kanawha St.

• Saturday, 09 August, 2014

Chris, the electrician, reported there were only five

crew on site today, from the electrical

subcontractors. The rest of the crew had this

summer Saturday off, and the electricians were

making use of the empty site. Chris also reported

that on a typical day, in addition to the Baker

Cement crew, there were electrician, plumbing,

rebar, and metal subcontractors on site.

• Friday, 08 August, 2014

At 6:30A a flatbed offloaded a baby backhoe that

parked in the first parking place headed West on

Kanawha St -- across Kanawha from the large,

orange “No Construction Vehicles Allowed” sign;

not sure if this equipment belongs to Grunley. The

crane was at full blast in the AM shifting supplies

and delivering cement, and the crew spent the

day pouring and managing the new cement.

• Thursday, 07 August, 2014

Met Rob Soper, Senior Site Supervisor for Grunley,

this morning -- as patient and friendly in person as

in emails. He explained much of the Southeast

corner that is lagging behind will not be part of

the building, and so does not command the same

priority. He also confirmed the following: At the

very bottom of the site is level one, which is

parking, and level two which is parking. Then

comes that schizophrenic level, level three, which

Rob called the cellar and the Building Blog has

been calling the ground floor; when driving in from

the gate, the road leads into the building level

three. The fourth level is the first floor, which is

the pedestrian entrance for the building. And the

fifth level is the second floor of the building. It is

this fifth level that received most of the attention

today.

• Wednesday, 06 August, 2014

The fifth level gang forms now spread across the

West side of the site. The crew continued

preparing for the cement on the West fifth level

and the East fourth. We saw a first for us; the

crane shifted a bucket of cement to the fifth

level, one of the crew removed one of the fifth

level gang form tiles, and the cement was pour

through the fifth level on to the fourth level

below. Way cool.

• Tuesday, 05 August, 2014

The fifth level gang forms now spread across the

West side of the site. The crew continued

preparing for the cement on the West fifth level

and the East fourth. We saw a first for us; the

crane shifted a bucket of cement to the fifth

level, one of the crew removed one of the fifth

level gang form tiles, and the cement was pour

through the fifth level on to the fourth level

below. Way cool.

• Tuesday, 05 August, 2014

The cement trucks brought loads for the NE

corner, fourth level, as the crew erected gang

forms for additional fifth level walls in the NW

quad.

• Monday, 04 August, 2014

Lots of activity weaving wire and rebar grids for

fourth level. On the Northwest side, the gang

forms we’re removed to expose the concrete

pillars. Work on the Southeast corner finally

started to catch up with the rest of the site

[end page]