Previous / Next
Monday, 02 December, 2013 to
Sunday, 08 December, 2013
Blog, Photos and Videos in reverse chronology.
Select thumbnail at the left for larger photo.
☆ Video
Sunday, 08 December, 2013
- Included Sunday in this week, so the first snow
of the season could be added to the photo gallery.
Saturday, 07 December, 2013
- The backhoe started early -- very early for a
Saturday morning -- digging in the southeast
corner and foreshadowing a busy day, but by
9:30A the large backhoe was idle and a new-to-
the-site baby backhoe took over the work -- at a
much lower noise level.
- The rest of the day, the onsite work was done
by the crew on the Kanawha retaining wall -- for
forklift and baby backhoe supporting them.
Friday, 06 December, 2013
- At 7A for two hours, the crew and their trucks
gathered at the entrance -- deciding if the rain
would go away or they would. The rain won; there
was no construction activity.
- At 10A the forklift unloaded a delivery of lumber
and around noon there was another delivery.
- At 3:18A another small bulldozer arrived along
with another wave of rain.
Thursday, 05 December, 2013
- Activity was less frenetic today. Work on the
retaining wall moved front-and-center on
Connecticut Ave. The backhoe and bulldozer
focused on digging and trucking the southeast
side, and the Jurassic Giraffe continued digging
holes on the far east side. At 8:15A the smaller
construction trailer was hoisted up next to the
larger construction trailer against the southeast
side.
Wednesday, 04 December, 2013
☆ YouTube Video - Slow Start To Busiest Day So
Far
The day started with the activity off camera; the
backhoe helped with the Kanawha retaining wall
to the far southwest, and the Jurassic Giraffe did
its usual digging on the far northwest corner.
However, by 9A the site was a beehive of dump
trucks, with the new bulldozer helping the
backhoe load. And the Jurassic Giraffe moved to
the east side, where the backhoe cleared away
the cement drive yesterday. At 9:40 another
construction trailer was delivered. This was
definitely the busiest construction day so far.
(1:38 min)
Tuesday, 03 December, 2013
- YouTube Video
The site manager and crew arrived late at 7:20A;
perhaps they were stuck in the infamous Military
Road traffic, shown at the left of the screen.
When work began, the backhoe helped pull dirt
from Kanawha retaining wall, then ripped up the
east side cement drive, loaded the cement pieces
into a dump truck, and spread a dump truck load
of gravel in place of the drive. About 11:30A, a
medium-sized bulldozer joined the site equipment.
The Jurassic Giraffe started in northwest corner
but went idle after about an hour; another new
piece of equipment -- a man-in-a-basket mover --
was used to repair the Jurassic Giraffe. Again, the
human crew continued exposing and building the
Kanawha St. retaining wall. (3:12 min)
Monday, 02 December, 2013
- YouTube Video
The backhoe buried the pool of water in the
center of the site, then proceeded to pull down
the old retaining wall on the far northeast side of
the site -- the wall between the site and 3710
Military Rd -- and spent the rest of the day
dancing around the site. A wood chipper was
brought to the far east side of the site to make
short work of several large tree branches. The
crew continued exposing and building the
Kanawha St. retaining wall, and the Jurassic
Giraffe continued digging hole on the Military side.
(1:22 min)
[end page]